PESHAWAR: Peshawar Electric Supply Company (PESCO) has issued a schedule of temporary power outage in different areas due to work on the 220 KV Nowshera to Swabi double circuit transmission line.
According to the issued notification, shutdown has been approved for construction, stringing, testing and commissioning of the transmission line, under which power supply of 132 KV transmission lines and various 11 KV feeders will remain suspended.
In the first phase of the schedule issued by PESCO, power supply will remain suspended daily from 9 am to 5 pm from November 11 to November 18, 2026. In this phase, work will be done on the transmission line between Tower No. 121 and 122, due to which the 132 KV grid station Charsadda will be affected